Construction, 2026
Secondary Flotation Plant
A secondary flotation circuit engineered to recover gold locked in tailings and transform 1.4 million tonnes of dormant material into value, relieving pressure on the main plant while improving water recycling and reducing environmental waste.
Overview
A secondary flotation plant engineered to recover gold locked in tailings and convert dormant material into value, relieving pressure on the main plant while improving water recycling and reducing environmental waste.
The project turns a waste liability into a revenue stream, and is a working example of the green-mining principles Terra-Tara applies across its operations.
Project highlights
- Recover gold locked in tailings from Levees 6 and 7
- Transform 1.4 million tonnes of dormant tailings into value
- Relieve pressure on the main plant while maintaining overall throughput
- Reduce environmental waste and improve water recycling and management
Progress to date
Civil works across the plant footprint are complete.
- Flotation concentrate, condition and tails tank plinths completed
- Blower base plinths completed
- Main cell plinths, bundwalls and sump completed
Next phase
- Begin earthworks for the raw water tank
- Complete drainage design and set-out
- Receive the next batch of flotation equipment
- Complete mechanical installation adjudication and electrical and instrumentation quotations